A number of roadworks around the north have returned this week as the six-week festive pause comes to an end.
From Monday, the break for all non-essential works set by the Department of Infrastructure (DfI) came to an end after being in place since November 25.
The annual moratorium is in place to help ease congestion during the busy Christmas period.
More: More traffic misery expected in Belfast as NI Water set to begin next phase of sewer relining work
In Belfast, the Sydenham Bypass resurfacing work was halted a few days early due to a weather warning at the time.
Work on the busy arterial route is among those which has recommenced from January 6 onwards.
Sydenham Bypass
The city-bound carriageway will be closed between Tillysburn and the M3 on weeknights from 10pm to 6am.
Four weekend closures are also anticipated before work is completed – the first of these closures is set to take place on 10 January, with the city-bound carriageway closed from 10pm on Friday until 6am on Monday.
DfI added that some weeknight and weekend closures may also be required on the country-bound lanes to ensure safety.
Work is expected to be completed by early March, depending on weather.
Shore Road, Belfast
The next phase of sewer relining by NI Water sees city-bound lanes at Seaview closing on the Shore Road in Belfast.
Temporary traffic lights will control two-way traffic (one lane in each direction) and will be manned during peak hours in the morning and evenings for approximately three weeks.
Saintfield Road and Knockbracken Road (A24)
Phase 3 and 4 of the works are to recommence, with the Knockbracken Road closed and a 30mph speed limit in place on Saintfield Road near the works.
City-bound traffic on the Saintfield Road is reduced to one lane as a new layout is constructed, a retaining wall is put in place and pedestrian facilities are enhanced.
Upper Newtownards Road (A20)
Phoenix Energy will recommence works on their network on the section of the road from Carrowreagh Road to Hawthornden Way.
Latest Update: Upper Newtownards Road Reinforcement
— Phoenix Energy (@phoenixni) October 25, 2024
This weekend, Saturday 26th and Sunday 27th October, works will take place on the Upper Newtownards Road, at the Ballyregan Road junction. For further details on these works please visit https://t.co/QyaLDEPd9K pic.twitter.com/Dgwm1WWDzJ
The latest phase to recommence covers the Stoney Road junction moving citybound to Hawthornden Way, with lane closures meaning one lane will be open in both directions.
Works are expected to be completed by April.
Derriaghy Road, Dunmurry
The Cutts Junction road safety improvement works are to recommence, impacting the busy McKinstry Road/Derriaghy Road/Cutts junction area.
From mid-November, the Derriaghy Road is to be closed for 20 weeks.
Diversions are in place and the department encourages road users to plan alternative routes.
Foyle Street, Derry
NI Water infrastructure works will see the city centre street closed again to all traffic apart from taxis.
Foyle Street is home to the city’s bus depot and a number of businesses.
The work is expected to be completed by the summer.
Shore Road, Strangford (A2)
Resurfacing work on the A2 Shore Road sees daily road closures in place from 8am to 5pm on the section of the road between Strangford Village and Kilclief.
Work is expected to run until March 14 and an alternative route is to be sign-posted during closure times.
Caledon Main Street, Co Tyrone (A28)
Carriageway strengthening and resurfacing on Main Street in Caledon to Finglush Road will operate daily between 9am and 4.30pm until January 17.
Diversions are in place and work is expected to cause delays between 5 and 15 minutes.